Click Here to View This Page on Production Frontend
Click Here to Export Node Content
Click Here to View Printer-Friendly Version (Raw Backend)
Note: front-end display has links to styled print versions.
Content Node ID: 380067
SEO Title
Vegas Bets Big on New Runway
Subtitle
McCarran has begun a runway resurfacing project.
Subject Area
Channel
Content Body
A $67 million resurfacing project on the 14,500-foot main runway at Las Vegas McCarran International has begun. Runway 7L/25R, which handles one third of the city’s annual aviation traffic, will be closed for two six-month-long periods. The eastern half of the runway is currently undergoing removal of the asphalt and replacement with more durable concrete, a job that is scheduled to last until May, allowing full capacity for the peak summer months. The second half of the project, which is financed with FAA grants and airport-generated funds, will start next October on the western half of the runway and conclude in May 2016.
Expert Opinion
False
Ads Enabled
True
AIN Story ID
019TouchingbasesAINDec14EditedByAY_NM
Content Label
Publication Date (intermediate)
AIN Publication Date
----------------------------